The 2026 Permitting Reform Bill Explained

The U.S. Senate passed the Bipartisan American Affordability and Jobs Act of 2026, 62 to 33. Learn how the bill would change approvals for power plants, power lines and data centers, who would pay for grid upgrades, and what happens next.

Share
Steel towers carry high voltage power lines across dry grassland under a blue sky.
The McNary to John Day transmission line in Washington state. Bonneville Power Administration photo, public domain, via Wikimedia Commons, cropped.

What Is the Permitting Reform Bill?

The Bipartisan American Affordability and Jobs Act of 2026 is a U.S. bill that changes how power plants, power lines, pipelines, mines and data centers win approval in the United States. The U.S. Senate passed it 62 to 33 on November 19, 2026, with five senators not voting. It is not law yet.

💡
A data center is a building full of computers that store data and run online services, cloud storage and artificial intelligence.

Before a U.S. government agency approves a large project, the National Environmental Policy Act of 1969 requires an environmental review. Under the bill:

💡
An environmental review is a study of how a project can affect air, water, land, wildlife and nearby communities.
  • Deadlines stay at one year for a short review and two years for a full review.
  • The agency must decide within 45 days after a full review is final.
  • Anyone suing over the review must file within 150 days, in a U.S. court of appeals. The limit today can reach six years.
  • A court that finds a flaw sends the review back. The agency gets 180 days to fix it, and the project can keep going.
  • Once a project holds every U.S. permit it needs, agencies cannot cancel or change those permits, except for fraud, permit violations, court orders and threats to public health, safety or national security.

The Federal Energy Regulatory Commission, the U.S. agency that oversees power lines between states, gains the power to approve a major line if a state rejects it or fails to act. States still decide first. Article 1 of the U.S. Constitution gives Congress the power to make such laws and to regulate trade between states.


Why Did It Happen?

Demand for electricity in the United States is rising, driven by data centers for artificial intelligence. Lawmakers in both major U.S. parties have said slow approvals delay projects and raise energy costs, and lawsuits over environmental reviews can hold up a project for years.

Four senators wrote the bill: Republicans Shelley Moore Capito of West Virginia and Mike Lee of Utah, and Democrats Martin Heinrich of New Mexico and Sheldon Whitehouse of Rhode Island. Senators placed the text inside H.R. 2347, a bill the U.S. House of Representatives passed on April 27, 2026. That bill, the Survivor Justice Tax Prevention Act, ends U.S. income tax on damages paid to survivors of sexual assault, and that part stays in the new version. Because the House already passed H.R. 2347, the House can now vote on the Senate version directly.

Other places have also set permit deadlines. The European Union, for example, limits permits for renewable energy projects to 12 months in chosen zones and two years elsewhere under Directive (EU) 2023/2413.



How Does It Affect People?

Electricity customers get a new protection. A new data center may need new power plants, batteries and lines, and under the bill other customers pay none of that added cost. The owner must give the utility a financial guarantee before the utility builds and still owes the costs if the data center shuts early. This rule covers data centers that connect after the bill becomes law.

💡
A utility is the company that delivers electricity to homes and businesses in an area.

The commission gets 270 days to change its 1994 rules on power line prices, so that data centers pay for the existing grid and for new upgrades.

💡
The grid is the network of power plants and power lines that carries electricity.

Builders of energy projects get quicker approvals that are harder to undo. The American Clean Power Association, which speaks for wind and solar companies, and the American Petroleum Institute, which speaks for oil and gas companies, both backed the bill.

Communities and Native American tribes get 150 days to sue instead of up to six years, and courts cannot stop a project over a flawed review alone. Opponents in the Senate said the bill weakens environmental protections and the rights of tribes. The U.S. Energy Information Administration also starts collecting data on how much electricity data centers use.


What Happens Next?

Only the Senate vote is decided, and every change above remains a proposal until the bill becomes law.

  • September 30, 2026: Capito introduced the bill as S. 5653.
  • November 18, 2026: The Senate adopted the new text 69 to 27 and voted 65 to 31 to end debate. Ending debate needed 60 of 100 senators.
  • January 3, 2027: The current U.S. Congress ends.

The House must pass the same text. If the House changes it, the bill goes back to the Senate. House leaders may bring the bill up under suspension of the rules.

💡
Suspension of the rules is a quick House process that limits debate and needs two thirds of members voting to pass a bill.

Any bill not passed before the current Congress ends must start over in the new Congress, which makes this a lame duck session bill. Democrats hold majorities in both chambers from January after the 2026 midterm elections. If both chambers agree, the bill goes to U.S. President Donald Trump, who has said he plans to sign it.


Sources


Disclaimer

This content was researched and organized with the assistance of Super Intelligence (SI) and is intended for educational and informational purposes only. MIMS Reports strives for accuracy, but information may change over time. Readers are encouraged to verify important information using official sources and consult qualified professionals when making legal, financial, medical, or other important decisions.